CEMEX Materials South West & Wales in Bristol last week completed a 660m3 pour for Knights Brown Construction to Accolade Wines in Avonmouth, a base for a new wind turbine. Supply from three Readymix plants and some articulated truckmixers supplied by Explore meant the pour was easily achieved within 11 hours.
The placement through CEMEX Go and tracking enabled the pour to be planned early and the customer was informed all day of how many loads had been batched.
Great team work, planning and collaboration between the Operations, Technical, Shipping and Supply chain meant this complex mix with numerous admixtures went smoothly.