Late last Wednesday evening saw the Mersey Gateway team complete the last 1,100m3 MSS pour on the project in 26 hours. Rob Preston from Merseylink rang to thank the team for their efforts in delivering the final section in a seamless fashion from their perspective.
Paul Cheeseman commented: “I would like to thank all the team involved over the past few days, where we have addressed and overcome issues arising during the pour without the client noticing any impact. Another much appreciated great effort.
The team even had enough time to enjoy an ice cream in the afternoon!”